How Long Does a Commercial Office Fit-Out Really Take?

A realistic timeline breakdown for bare-shell to move-in office projects — and the factors that accelerate or delay delivery.

How Long Does a Commercial Office Fit-Out Really Take?

Clients often ask for a single number: how many months? The honest answer depends on scope, shell condition, MEP complexity and decision speed. Here is a practical framework.

Typical phases

  1. Design & approvals — 3–6 weeks depending on landlord and local authority requirements.
  2. Civil & MEP rough-in — 4–8 weeks for a 5,000–10,000 sq ft office.
  3. Interiors & finishes — 6–10 weeks running parallel where possible.
  4. Snagging & handover — 1–2 weeks.

For a mid-size tech office of 8,000 sq ft, a well-coordinated project typically lands at 4–5 months from design kick-off to move-in.